Kyocera to Build Its Largest Plant in Japan, Increasing Production of Semiconductor Components

Expanded Sendai Plant Campus in Kagoshima will meet increasing demand for semiconductor packages powering ADAS, sensor cameras, 5G and more.

Kyocera Corporation today announced a plan to build the largest manufacturing facility it has ever operated in Japan, expanding production capacity for components including organic semiconductor packages and crystal device packages. A signing ceremony held April 20, 2022 was attended by Kagoshima Governor Koichi Shiota, Satsumasendai City Mayor Ryoji Tanaka, and Kyocera officials. Construction is scheduled to begin next month at the company’s Sendai Plant Campus in Kagoshima.

Three converging factors are creating strong demand for Kyocera’s organic semiconductor packages and crystal device packages. Smart vehicles are expanding the need for automotive cameras and high-performance processors used in Advanced Driver-Assistance Systems (ADAS) and autonomous driving. New communications infrastructures, including fifth-generation (5G) base stations and datacenters, are being deployed worldwide. In addition, the rising trend toward digitalization is expanding demand for electronic products ranging from personal computers and smartphones to consumer goods, industrial automation, and others.

Kyocera will open the new facility in October 2023 to serve these growing trends, aiming for a 4.5-fold increase in production capacity for organic packages at the Sendai Plant Campus, as well as a substantial increase in capacity for crystal device packages.

Kyocera will contribute to the community by stimulating economic development in Kagoshima, creating new employment opportunities through expanded production of semiconductor components in response to global demand.

Outline of New Facility

Name

Plant No.23 at Kyocera’s Kagoshima Sendai Campus

Address

2310-10 Taki-cho, Satsumasendai-shi, Kagoshima Prefecture, Japan

Total investment

Approximately 62.5 billion yen (approx. 488 million U.S. dollars)

Building footprint

12,380 m2 (133,257 f2), steel construction, 6 stories

Total area

65,530 m2 (705,359 f2)

Construction plan

Construction to begin May 2022

Facility to open October 2023

Production items

Organic packages, crystal device packages

Expected production level

Approximately 33 billion yen (approx. 258 million U.S. dollars) per year (April 2024-March 2025)